Skip to main content

XTM Connect – Oracle Content Management 1.0/Translation Requester Guide

Changing the translation project due date in the Translation Queue

You can only change a translation project's due date if the project's XTM Status is:

  • Sent

  • In progress

Additionally, you can only change the translation project due date provided that your Client administrator has selected the Enable users to change due dates in existing projects option when configuring the Oracle profile in the XTM CLOUD SETTINGS section.

You can:

To change a single translation project due date using the context menu icon:
  1. Find the translation project whose due date you want to change and select the context menu icon located on the far right side of the screen, in the project line.

  2. In the context menu icon, select the Change due date option.

    The Change due date popup is displayed and you are prompted to change the project(s) due date(s).

  3. In the Change due date popup, using the date picker, set a new date and:

    • to confirm that you want to change the project due date, select Save.

      A screen message confirms that you have saved the newly set due date for the project.

    • if you do not want to change the project due date, select Cancel.

      The Change due date popup closes.

To change a single or multiple translation projects due dates using the bulk Actions menu:
  1. Select the translation project or projects whose due dates you want to change by selecting the checkbox to the left of the project names.

  2. At the top of the screen, on the left, select the Actions menu.

  3. Select the Change due date option.

    The Change due date popup is displayed and you are prompted to change the project(s) due date(s).

  4. In the Change due date popup, using the date picker, set a new date and:

    • to confirm that you want to change the project(s) due dates, select Save.

      A screen message confirms that you have saved the newly set due date(s) for the project(s).

    • if you do not want to change the project(s) due date(s), select Cancel.

      The Change due date popup closes.