Importing translation projects

Translation projects are usually imported into Akeneo automatically. If automatic import fails (for example, due to network issues or if the Akeneo system is down), you can import a single or multiple projects manually. They will then be returned to Akeneo with the other finished projects in the Translation queue during the next synchronization run.

Note

You can only import projects manually if their XTM Status is Finished.

To import one or more translation projects using the Actions menu:
  1. Select the translation project or projects that you want to import. To do so, select the checkbox to the left of the project name.

  2. Select the Actions menu at the top of the screen, on the left.

  3. Select the Import option. An Import popup is displayed.

  4. In the popup:

    • To confirm that you want to import the projects, select Okay.

      Result: a screen message confirms that you have imported the projects.